Friday 1 September 2006 9.00am EDT
During the last week the observing schedule was replanned to include
an observation of SGR 1806-20 that was accepted as fast turn-around
Target Of Opportunity (TOO) on August 30. Loads were replanned and
uplinked on August 31. An observation of B2224+65 was impacted by the
TOO and will be rescheduled in a later load.
The schedule of targets for next week is shown below and includes an observation of XTE J1810-197 coordinated with ground-based observations. |
------------------------------------------
Radiation Belts Sep 3 RS Oph HRC-S/LETG Sep 4 M33 Field 2 ACIS-I SDSS J0750+4252 ACIS-S Sep 5 WR20a ACIS-I SDSS J0803+3022 ACIS-S Sep 6 Radiation Belts RS Oph HRC-S/LETG M33 Field 2 ACIS-I Sep 7 RXC J1147.3+5544 ACIS-S 1RXS J140654.5+525 ACIS-S Sep 8 RS Oph HRC-S/LETG Radiation Belts P14 ACIS-I Sep 9 P4 ACIS-I P3 ACIS-I P2 ACIS-I NGC 4194 ACIS-S NGC 5474 ACIS-S Sep 10 XMMU J2235.3-2557 ACIS-S XTE J1810-197 ACIS-S
------------------------------------------
All spacecraft subsystems continued to support nominal operations.