Friday 9 September 2011 9.00am EDT
During the last week Chandra completed the observing schedule as planned. A real-time procedure was executed on Sep 7 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer. The schedule of targets for the next week is shown below and includes an observations of GRB 110731A, which is a follow-up to a Target of Opportunity that was accepted on Aug 10, of XTE J1701-407, which was accepted as a Target of Opportunity on Aug 29, and of the Crab, from a series of Director's Discretionary Time TOO observations accepted on Dec 14. |
------------------------------------------
Radiation Belts Sep 10 A133-3 ACIS-I A133-4 ACIS-I Sep 12 1RXSJ054747.2-19560 ACIS-S GRB110731A ACIS-S Radiation Belts Sep 13 A133-4 ACIS-I Crab ACIS-S Sep 15 XTEJ1701-407 ACIS-S Radiation Belts A133F ACIS-I Sep 16 PSRJ1028-5819 ACIS-I A133-5 ACIS-I A133E ACIS-I Sep 17
------------------------------------------
All spacecraft subsystems continued to support nominal operations.