News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal (opens in new window)
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Operations CXO Status Report

Friday 5 October 2012 9.00am EDT

During the last week Chandra completed the observing schedule as planned.

Chandra passed through the 22nd and 23rd eclipses of the season on Sep 30 and Oct 3 respectively, with nominal power and thermal performance.

A demonstration of an update to the on-board ephemeris via commanding in the weekly loads was conducted on Oct 1. This successful demonstration will allow for more frequent ephemeris updates (once per orbit) which will reduce attitude errors at perigee by approximately a factor of four. A real-time procedure was executed on Oct 3 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer.

The schedule of targets for the next week is shown below and includes an observation of Parenago523_P2 coordinated with OVRO/CARMA.



------------------------------------------
Radiation Belts                     Oct  8
         NGC3324                ACIS-I
         Abell1758              ACIS-I       Oct  9
         M51                    ACIS-S       Oct 10
         Vega                   HRC-I
         Vega (4 obs)           HRC-S
         Parenago523_P2         ACIS-S
         J0252.0-1642           ACIS-I
         Abell2645              ACIS-I
         Radiation Belts                     Oct 11
         SPT-CLJ0446-5849       ACIS-I
         2XMMJ110145.0-61014    ACIS-I
         WR48a                  ACIS-S/HETG  Oct 12
         A773                   ACIS-I       Oct 13
         Radiation Belts                     Oct 14
         SPT-CLJ0446-5849       ACIS-I

------------------------------------------

All spacecraft subsystems continued to support nominal operations.